Filters
Question type

Study Flashcards

The main goal of retail layout is


A) minimizing material handling cost.
B) maximizing high-margin sales.
C) minimizing storage costs.
D) minimizing space required.
E) maximizing profitability per square foot of floor space.

F) A) and B)
G) A) and D)

Correct Answer

verifed

verified

A(n) ________ is a special product-oriented arrangement of machines and personnel in what is ordinarily a process-oriented facility.

Correct Answer

verifed

verified

Currently there are 5 tasks that need to be performed. These tasks, ABCDE, have required times of 2 minutes, 5 minutes, 4 minutes, 3 minutes, and 10 minutes respectively. The assembly line needs to produce 50 units per day to meet demand and can work for up to 7.5 hours each day. A. What is the required cycle time? B. What is the theoretical minimum # of workstations?

Correct Answer

verifed

verified

Required cycle time = Production time av...

View Answer

The assumptions necessary for a successful product layout include all of the following except


A) adequate volume for high equipment utilization.
B) standardized product.
C) volatile product demand.
D) All of the above are appropriate assumptions.
E) None of the above are an appropriate assumption.

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

Explain how a load-distance model helps solve problems in process layout.

Correct Answer

verifed

verified

The problem in process layout is to hold...

View Answer

Heuristics are problem-solving procedures that mathematically optimize the solution.

A) True
B) False

Correct Answer

verifed

verified

The minimum number of workstations depends upon the set of task times and the precedence chart, but not the number of units scheduled.

A) True
B) False

Correct Answer

verifed

verified

Cross-docking processes items as they are received, rather than placing them in storage; this helps explain why "warehouses" are now called "distribution centers."

A) True
B) False

Correct Answer

verifed

verified

One disadvantage of process-oriented layouts arises from


A) the use of special purpose equipment.
B) machine maintenance, which tends to seriously degrade the capacity of the entire system.
C) the use of specialized material handling equipment.
D) the need for stable demand.
E) the use of the general purpose machines and equipment.

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

A fabrication line and an assembly line are both types of repetitive and product-focused layout, but only the fabrication line utilizes workstations.

A) True
B) False

Correct Answer

verifed

verified

An insurance claims processing center has six work centers, any of which can be placed into any of six physical departmental locations. Call the centers 1, 2, 3, 4, 5, and 6, and the departments A, B, C, D, E, and F. The current set of assignments is A-3, B-1, C-6, D-2, E-4, and F-5. The (symmetric) matrix of departmental distances, in meters is 1234561−−5302015202−−401510103−−502054−−10355−−56−−\begin{array} { | c | c | c | c | c | c | c | } \hline & \mathbf { 1 } & \mathbf { 2 } & \mathbf { 3 } & \mathbf { 4 } & \mathbf { 5 } & \mathbf { 6 } \\\hline \mathbf { 1 } & - - & 5 & 30 & 20 & 15 & 20 \\\hline \mathbf { 2 } & & - - & 40 & 15 & 10 & 10 \\\hline \mathbf { 3 } & & & - - & 50 & 20 & 5 \\\hline \mathbf { 4 } & & & & - - & 10 & 35 \\\hline \mathbf { 5 } & & & & & - - & 5 \\\hline \mathbf { 6 } & & & & & & - - \\\hline\end{array} The matrix of work flow (estimated trips per day) is among centers ABCDEFA−−15200300B20−−50016010C050−−30030D306020−−700E400010−−60F00302050−−\begin{array} { | l | c | c | c | c | c | c | } \hline & \boldsymbol { A } & \mathbf { B } & \mathbf { C } & \mathbf { D } & \mathbf { E } & \mathbf { F } \\\hline \mathrm { A } & - - & 15 & 20 & 0 & 30 & 0 \\\hline \mathrm { B } & 20 & - - & 50 & 0 & 160 & 10 \\\hline \mathrm { C } & 0 & 50 & - - & 30 & 0 & 30 \\\hline \mathrm { D } & 30 & 60 & 20 & - - & 70 & 0 \\\hline \mathrm { E } & 40 & 0 & 0 & 10 & - - & 60 \\\hline \mathrm { F } & 0 & 0 & 30 & 20 & 50 & - - \\\hline\end{array} The firm estimates that each trip costs approximately $4. a. What is the cost of the current assignment? b. Use trial-and-error to find one improved assignment. c. What is that assignment, and what is its cost?

Correct Answer

verifed

verified

(a) The current assignment costs 14,000 ...

View Answer

McDonald's "Made by You" kitchen system represents a ________ use of layout decisions.

Correct Answer

verifed

verified

A manufacturing work cell has a takt time of 7 minutes and is staffed by 10 workers. If the work cell delivers 68 units each day find A. The total operation time B. The amount of time worked during the day for all 10 workers combined C. If the plant is open for only 8 hours per day, can the staff meet demand?

Correct Answer

verifed

verified

Total operation time = Workers required ...

View Answer

If the schedule calls for the production of 120 units per day and 480 minutes of production time are available per day, the maximum cycle time would be 4 minutes.

A) True
B) False

Correct Answer

verifed

verified

A(n) ________ addresses flow, allocates space, and responds to customer behavior.

Correct Answer

verifed

verified

Identify the four requirements for cellular production.

Correct Answer

verifed

verified

(1) identification of families of produc...

View Answer

________ is that element of balancing a work cell that superficially resembles cycle time.

Correct Answer

verifed

verified

A manufacturing work cell has a takt time of 5 minutes and is staffed by 7 workers. If the work cell delivers 61 units each day find A. The total operation time B. The amount of time worked during the day for all 10 workers combined C. If the plant is open for only 5 hours per day, can the staff meet demand?

Correct Answer

verifed

verified

A) Total operation time = Workers requir...

View Answer

Product-oriented layouts tend to have high levels of work-in-process inventories.

A) True
B) False

Correct Answer

verifed

verified

Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. a. Draw the precedence diagram for the set of tasks. b. Calculate the theoretical minimum number of workstations. c. Balance this line using the longest task time heuristic. d. What tasks are assigned to which stations? e. Does the solution have the minimum number of stations? Explain. f. How much idle time is there, summed over all workstations? g. What is the efficiency of this line?  Work Task  Task Time  (seconds)  Immediate  Predecessor(s)  A 70− B 60 A C 120 B D 60− E 240C,D F 100 A G 190E,F\begin{array} { | c | c | c | } \hline \text { Work Task } & \begin{array} { c } \text { Task Time } \\\text { (seconds) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 70 & - \\\hline \text { B } & 60 & \mathrm {~A} \\\hline \text { C } & 120 & \mathrm {~B} \\\hline \text { D } & 60 & - \\\hline \text { E } & 240 & \mathrm { C } , \mathrm { D } \\\hline \text { F } & 100 & \mathrm {~A} \\\hline \text { G } & 190 & \mathrm { E } , \mathrm { F } \\\hline\end{array}

Correct Answer

verifed

verified

The theoretical minimum number of workst...

View Answer

Showing 41 - 60 of 171

Related Exams

Show Answer