Draw the AOA and AON networks for the following project and calculate the minimum project duration. Draw the AOA and AON networks for the following project and calculate the minimum project duration.

Correct Answer

verifed

verified

blured image blured image blured image Minimum duration ...

View Answer

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

A) True
B) False

Correct Answer

verifed

verified

If an activity whose normal duration is 55 days can be shortened to 50 days for an added cost of $45,000,the crash cost per period is


A) $9,000.
B) $500.
C) $900.
D) $4,500.
E) $45,000.

F) B) and C)
G) D) and E)

Correct Answer

verifed

verified

Which of the following statements regarding critical paths is true?


A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.

F) None of the above
G) All of the above

Correct Answer

verifed

verified

The critical path can be determined by use of either the "forward pass" or the "backward pass."

A) True
B) False

Correct Answer

verifed

verified

The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.

Correct Answer

verifed

verified

Which of the following statements regarding PERT times is true?


A) The expected time is an estimate of the time an activity will require if everything goes as planned.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The expected time estimate is calculated as t = (a + 4m + b) /6.
D) The pessimistic time estimate is an estimate of the minimum time an activity will require.
E) The most likely time estimate is an estimate of the maximum time an activity will require.

F) B) and D)
G) D) and E)

Correct Answer

verifed

verified

The project organization works best when which of the following conditions are satisfied?


A) Work can be defined with a specific goal and deadline.
B) The job is typical and familiar to the existing organization.
C) The work contains simple tasks requiring no special skills.
D) The project is temporary but unimportant to long-term organizational success.
E) The project is confined to one functional area.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

The ________ distribution is used by PERT analysis to calculate expected activity times and variances.


A) Normal
B) Beta
C) Alpha
D) Gaussian
E) Binomial

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

________ is a network technique using only one time factor per activity that enables managers to schedule,monitor,and control large and complex projects.

Correct Answer

verifed

verified

Critical path method or CPM

The phases of project management are


A) planning,scheduling,and controlling.
B) planning,programming,and budgeting.
C) planning,organizing,staffing,leading,and controlling.
D) different for manufacturing projects than for service projects.
E) GANTT,CPM,and PERT.

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando,Florida.

Correct Answer

verifed

verified

Prior to beginning actual construction,r...

View Answer

Gantt charts give a timeline for each of a project's activities,but they do not adequately illustrate the interrelationships between the activities and the resources.

A) True
B) False

Correct Answer

verifed

verified

True

What are some of the ethical issues faced by project managers? Which of these are likely to occur before a project begins,which are likely to occur while the project is underway,and which may occur after a project is complete? Illustrate any one of these from recent news.

Correct Answer

verifed

verified

A project manager can be exposed to a wi...

View Answer

Briefly discuss what is meant by critical path analysis.What are critical path activities and why are they important?

Correct Answer

verifed

verified

The critical path consists of those task...

View Answer

Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

Correct Answer

verifed

verified

Add the variances of the activ...

View Answer

What is the basic difference between PERT and CPM?

Correct Answer

verifed

verified

The basic difference between P...

View Answer

Which of the following statements regarding EllisDon is false?


A) Its competitive advantage is project management.
B) It is a Canadian leader in engineering and construction project management.
C) EllisDon believes in becoming deeply involved in each project.
D) EllisDon believes in a hands-off approach to project management.
E) All of the above are false.

F) C) and E)
G) All of the above

Correct Answer

verifed

verified

D

Explain why the critical path is the longest,not the shortest,path through a network.

Correct Answer

verifed

verified

Critical path is that set of activities ...

View Answer

An activity on a PERT network has these time estimates: optimistic = 1,most likely = 2,and pessimistic = 5.Its expected time is


A) 2.00.
B) 2.33.
C) 2.67.
D) 8.00.
E) 23.3.

F) B) and E)
G) C) and E)

Correct Answer

verifed

verified