Shortening the project's duration by deleting unnecessary activities is called "project crashing."

A) True
B) False

Correct Answer

verifed

verified

Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration

Correct Answer

verifed

verified

blured image (A)Two paths are possible,ACDE and ABE....